In a time study the standard time is computed by
A) multiplying the elemental average time by the rating factor
B) dividing the average elemental time by the rating factor
C) multiplying the normal cycle time by the rating factor
D) multiplying the normal cycle time by one plus the allowance factor
Correct Answer:
Verified