Table 7.12 A Company Desires to Set Up a Line to Produce

Question 102

Multiple Choice

Table 7.12
A company desires to set up a line to produce 60 units per hour.The work elements and their precedence relationships are as follows.
Table 7.12 A company desires to set up a line to produce 60 units per hour.The work elements and their precedence relationships are as follows.    -Use the information in Table 7.12.What is the theoretical minimum number of stations? A) 3 B) 4 C) 5 D) 6
-Use the information in Table 7.12.What is the theoretical minimum number of stations?


A) 3
B) 4
C) 5
D) 6

Correct Answer: