Deck 1: Measurement Methods for Construction Work

Full screen (f)
exit full mode
Question
Brick walls are measured in sq. m if the thickness of the wall is

A)10 cm
B)15 cm
C)20 cm
D)30 cm
Use Space or
up arrow
down arrow
to flip the card.
Question
The brick work is not measured in cu m in case of

A)one or more than one brick wall
B)brick work in arches
C)reinforced brick work
D)half brick wall
Question
The following item of earth work is not measured separately.

A)brick work
B)site clearance
C)plastering work
D)concrete work
Question
The measurement is not made in square meters in case of

A)d.p.c. (damp proof course)
B)form works
C)concrete jeffries
D)r.c. chhajja
Question
Pick up the incorrect statement from the following:

A)dimensions are measured to the nearest 0.01 m
B)areas are measured to the nearest 0.01 sq.m
C)cubic contents are measured to the nearest 0.1 cum
D)weights are measured to the nearest 0.001 tonnes
Question
The item of steel work which is measured in sq.m, is

A)collapsible gates
B)cement work
C)brick work
D)steel work
Question
The damp proof course (D.P.C.) is measured in

A)cub. m
B)sq. m
C)meters
D)rmt
Question
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

A)0.90 m3
B)0.94 m3
C)0.98 m3
D)1.00 m3
Question
According to ISI method of measurement, the order of the sequence is

A)length, breadth, height
B)breadth, length, height
C)height, length, breadth
D)breath, length, height
Question
Carpet area does not include the area of

A)hall area
B)bath room and lavatory
C)bed room area
D)plot area
Question
The item of the brick structure measured in sq.m, is

A)reinforced brick work
B)broken glass coping
C)brick edging
D)brick work in arches
Question
The 'centre line method' is specially adopted for estimating

A)bridge buildings
B)rectangular buildings
C)steel buildings
D)earthen building
Question
The order of Taking dimensions is

A)length, breadth, height
B)breadth, length, height.
C)height, breadth, length
D)breadth, length, height
Question
Pick up the item of work not included in the plinth area estimate

A)wall thickness
B)room area
C)w.c. area
D)courtyard area
Question
If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by

A)mid-section formula
B)center line methods
C)long wall short wall methods
D)rate analysis methods
Question
In the mid-section formula

A)the mean depth is the average of depths of two consecutive sections
B)the area mean
C)same as prizmoidal formula
D)same as trapezoidal formula
Question
The correct Prismoidal formula for volume is

A)d [first area + last area + ? even area + 2 ? odd areas]
B)d/3 [first area + last area + 4 ? even area + 2 ? odd areas]
C)d/3 [first area + last area + 2 ? even area + 4 ? odd areas]
D)d/6 [first area + last area + 2 ? even area + 4 ? odd areas]
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/17
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 1: Measurement Methods for Construction Work
1
Brick walls are measured in sq. m if the thickness of the wall is

A)10 cm
B)15 cm
C)20 cm
D)30 cm
10 cm
2
The brick work is not measured in cu m in case of

A)one or more than one brick wall
B)brick work in arches
C)reinforced brick work
D)half brick wall
half brick wall
3
The following item of earth work is not measured separately.

A)brick work
B)site clearance
C)plastering work
D)concrete work
site clearance
4
The measurement is not made in square meters in case of

A)d.p.c. (damp proof course)
B)form works
C)concrete jeffries
D)r.c. chhajja
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
5
Pick up the incorrect statement from the following:

A)dimensions are measured to the nearest 0.01 m
B)areas are measured to the nearest 0.01 sq.m
C)cubic contents are measured to the nearest 0.1 cum
D)weights are measured to the nearest 0.001 tonnes
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
6
The item of steel work which is measured in sq.m, is

A)collapsible gates
B)cement work
C)brick work
D)steel work
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
7
The damp proof course (D.P.C.) is measured in

A)cub. m
B)sq. m
C)meters
D)rmt
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
8
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

A)0.90 m3
B)0.94 m3
C)0.98 m3
D)1.00 m3
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
9
According to ISI method of measurement, the order of the sequence is

A)length, breadth, height
B)breadth, length, height
C)height, length, breadth
D)breath, length, height
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
10
Carpet area does not include the area of

A)hall area
B)bath room and lavatory
C)bed room area
D)plot area
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
11
The item of the brick structure measured in sq.m, is

A)reinforced brick work
B)broken glass coping
C)brick edging
D)brick work in arches
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
12
The 'centre line method' is specially adopted for estimating

A)bridge buildings
B)rectangular buildings
C)steel buildings
D)earthen building
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
13
The order of Taking dimensions is

A)length, breadth, height
B)breadth, length, height.
C)height, breadth, length
D)breadth, length, height
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
14
Pick up the item of work not included in the plinth area estimate

A)wall thickness
B)room area
C)w.c. area
D)courtyard area
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
15
If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by

A)mid-section formula
B)center line methods
C)long wall short wall methods
D)rate analysis methods
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
16
In the mid-section formula

A)the mean depth is the average of depths of two consecutive sections
B)the area mean
C)same as prizmoidal formula
D)same as trapezoidal formula
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
17
The correct Prismoidal formula for volume is

A)d [first area + last area + ? even area + 2 ? odd areas]
B)d/3 [first area + last area + 4 ? even area + 2 ? odd areas]
C)d/3 [first area + last area + 2 ? even area + 4 ? odd areas]
D)d/6 [first area + last area + 2 ? even area + 4 ? odd areas]
Unlock Deck
Unlock for access to all 17 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 17 flashcards in this deck.