Deck 22: Workcenter Scheduling
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/125
Play
Full screen (f)
Deck 22: Workcenter Scheduling
1
A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.
False
2
Priority rules are the rules used to obtain a job sequence in production scheduling.
True
3
In production scheduling, the process of determining which job to start first on some machine or in some workcenter is known as sequencing or priority sequencing.
True
4
Under the STR/OP sequencing priority rule, orders with the jobs with the longest STR/OP are run first.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
5
A shop-floor control system is a system that uses data from the shop floor as well as data processing files to maintain and communicate status information on shop orders and workcenters.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
6
The LCFS and Johnson's priority rules are basically the same except LCFS uses due dates as a major determiner of job sequence.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
7
Using the random order or "whim" priority rule to sequence production jobs means that supervisors or operators select whichever job they feel like running.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
8
Theoretically, all schedules are feasible when finite loading is used.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
9
In infinite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the workcenter considered.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
10
One of the principles of workcenter scheduling is to match workcenter input information to what the worker can actually do.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
11
The assignment method of job sequencing is a special case of the transportation method of linear programming.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
12
Initiating performance of scheduled work is commonly termed "dispatching" of orders.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
13
The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
14
Johnson's rule, a priority rule used in sequencing production jobs, is used only in production situations where we are dealing with one machine or one stage of production activity.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
15
Shop-floor control (or production activity control) can involve expediting late and critical orders.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
16
Shop-floor control (or production activity control) can involve reviewing the status and controlling the progress of orders as they are being worked on.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
17
A backward schedule tells when an order must be started in order to be done by a specific date.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
18
One of the principles of workcenter scheduling is that, while certainty of standards, routings, and so forth is not entirely possible in a shop, certainty should always be an objective to work toward.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
19
A workcenter is a physical area of the business in which productive resources are organized and work is completed.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
20
In finite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the workcenter considered.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
21
Most process are both labor- and machine-limited.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
22
The goal in developing a service staffing plan is to minimize overtime.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
23
One of the principles of workcenter scheduling is that once started, a job should not be interrupted.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
24
From an operations standpoint, one of the goals of the firm under the theory of constraints is to increase throughput while simultaneously reducing inventory and reducing operating expense.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
25
Mr. Goldratt's "theory of constraints" is useful only in manufacturing settings.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
26
According to the theory of constraints, capacity is the time available for production.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
27
According to the theory of constraints, the term "productivity" is defined as all those actions that bring a company closer to its goals.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
28
OPT stands for optimal purchasing technique.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
29
MES and SES are acronyms for "manufacturing environment scheduler" and "service environment scheduler" systems, respectively.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
30
When work is scheduled in detail using the setup and run time required for each order, then theoretically all schedules will be feasible.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
31
Most scheduling systems develop their schedules without consideration of capacity.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
32
Operations scheduling is at the heart of what is currently referred to as Manufacturing Scheduling System (MSS).
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
33
According to the theory of constraints, a non-bottleneck is any resource where capacity is less than the demand placed on it.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
34
Scheduling hourly work times using the "first-hour principle" ensures that no excess labor will be used during the work shift.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
35
Synchronous manufacturing refers to the entire production process working together in harmony to achieve the goals of the firm.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
36
One of the principles of workcenter scheduling is that the effectiveness of any shop should be measured by speed of flow through the shop.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
37
According to the theory of constraints, it is wrong for manufacturers to try to match capacity with demand by attempting to balance capacity across a sequence of processes. Unbalanced capacity is better.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
38
Dr. Eli Goldratt feels that the goal of a firm is to make useful products efficiently.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
39
According to the theory of constraints, a bottleneck is any resource whose capacity is greater than the demand placed on it.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
40
The operational measure of throughput is "the rate at which money is generated by the system through production of goods and services that might be sold."
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
41
On an assembly line, a process batch can be infinite.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
42
The "dollar days" inventory measurement results from a complex algorithm used to compute individual units of inventory and their respective ordering and holding costs.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
43
Buffer inventory in front of a bottleneck is called a time buffer.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
44
The synchronous manufacturing approach uses backward scheduling.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
45
A process batch should be no larger than the transfer batch.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
46
The "dollar days" inventory measurement can be used in purchasing to discourage large work-in-process and producing earlier than is needed.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
47
An MRP system can allow for product rejects by building a larger batch than is demanded, but a JIT system cannot tolerate poor quality.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
48
According to the theory of constraints, a capacity-constrained resource (CCR) is one whose utilization is close to capacity and could be a bottleneck if it is not scheduled carefully.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
49
On an assembly line, a transfer batch can be one unit.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
50
One way to find a bottleneck is to run a capacity resource profile.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
51
Smaller transfer batches give lower work-in-process inventory and faster product flow.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
52
JIT requires work-in-process when used with Kanban so there is inventory to pull. When compared to synchronous manufacturing, this is viewed as a negative aspect of JIT.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
53
According to the theory of constraints, throughput is the rate at which product is passed through the manufacturing system.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
54
A way to find a bottleneck is to use one's knowledge of a particular plant, look at the system in operation, and talk with supervisors and workers.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
55
The "dollar days" inventory measurement may be used to focus management's attention on where inventory is located.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
56
Rather than try to adjust the master production schedule to change resource loads, it is more practical to control the flow at each bottleneck or CCR to bring capacities in line.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
57
A synchronous manufacturing system does not have excess capacity throughout the system, except for the bottleneck.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
58
Larger transfer batches give shorter lead times and lower inventories, and there is more material handling than smaller transfer batches.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
59
Transfer batch is another term for process batch.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
60
According to the theory of constraints, throughput is the rate at which money is generated by the system through sales.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
61
In a process sequence where a product flows from process A to process B, process B is called the dependent process.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
62
The effects of statistical variations in processing times in a dependent sequence will eventually cancel themselves out due to the law of averages.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
63
MRP uses forward scheduling, beginning with the master production schedule.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
64
In this type of production, the typical scheduling approach is infinite forward scheduling typical: priority control; typically labor-limited, but often machine-limited; often responding to just-in-time orders from customers or MRP due dates.
A) Projects
B) Mid-volume manufacturing
C) Continuous processes
D) Low-volume workcenters
E) High-volume manufacturing
A) Projects
B) Mid-volume manufacturing
C) Continuous processes
D) Low-volume workcenters
E) High-volume manufacturing
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
65
Looking at the loads that are placed on each resource by the products that are scheduled through them is called process flow profiling.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
66
Labor cost and machine hours are ignored in valuing inventory in TOC.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
67
Because of statistical fluctuation (processing times vary around an average processing time), dependent sequences can operate without any inventory between workstations.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
68
In a process sequence where a product flows from process A to process B, process A is called the mother process.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
69
JIT requires vendors to be located nearby. When compared to synchronous manufacturing, this is viewed as an advantage of JIT.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
70
In this type of production, the typical scheduling approach is infinite, forward scheduling of jobs: usually labor-limited, but certain functions may be machine-limited (a heat-treating process or a precision machining center, for example); priorities determined by MRP due dates.
A) Projects
B) Mid-volume manufacturing
C) Continuous processes
D) Low-volume workcenters
E) High-volume manufacturing
A) Projects
B) Mid-volume manufacturing
C) Continuous processes
D) Low-volume workcenters
E) High-volume manufacturing
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
71
There is little to be gained by saving time on a bottleneck operation since it only increases the capacity of one operation.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
72
There is no problem with inventory as long as it is eventually used or sold.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
73
In synchronous manufacturing thinking, unbalanced capacity is best.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
74
The term "dependent events" refers to a process sequence.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
75
Statistical fluctuation refers to the normal variation about a mean or average.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
76
Departments within a firm often are at odds with each other because reward systems are often not synchronized with the basic goal of the firm: to make money.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
77
In a process sequence where a product flows from process A to process B, process B is called the contingent process.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
78
Throughput is all production. That is, everything that makes it to finished goods.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
79
Since there are so many nonbottleneck operations, an hour saved on them is very valuable.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck
80
JIT requires a stable production level. When compared to synchronous manufacturing, this is viewed as a negative aspect of JIT.
Unlock Deck
Unlock for access to all 125 flashcards in this deck.
Unlock Deck
k this deck