Deck 3: Owners, Designers, and Constructors
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/20
Play
Full screen (f)
Deck 3: Owners, Designers, and Constructors
1
Design Professionals are always bound by the same Contract the Owner requires the Constructor to perform
False
2
Bid shopping is a good way to make money
False
3
When dealing with a case, you can expect
A) the judge to be fairer than the jury
B) the jury to be fairer than the judge
C) that neither the judge or jury will be fair
D) that you will probably be better off if you can find a solution outside of a courtroom
A) the judge to be fairer than the jury
B) the jury to be fairer than the judge
C) that neither the judge or jury will be fair
D) that you will probably be better off if you can find a solution outside of a courtroom
D
4
In Design - Bid - Build
A) the Owner is contractually in the middle between the Designers and the Constructor
B) the Designer is caught in the middle between the Owner and the Constructor
C) the Constructor is contractually in the middle between the Owner and Designer
D) the problem is nobody wins
A) the Owner is contractually in the middle between the Designers and the Constructor
B) the Designer is caught in the middle between the Owner and the Constructor
C) the Constructor is contractually in the middle between the Owner and Designer
D) the problem is nobody wins
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
5
There are two main types of construction
A) tall and flat
B) x and y
C) up and down
D) vertical and horizontal
A) tall and flat
B) x and y
C) up and down
D) vertical and horizontal
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
6
Although not written in the contract
A) everyone will answer to civil authorities if necessary
B) everyone has the duty to cooperate
C) no one can blame another until the actual incident is completed
D) no one can bring a case against another until the contract is completed
A) everyone will answer to civil authorities if necessary
B) everyone has the duty to cooperate
C) no one can blame another until the actual incident is completed
D) no one can bring a case against another until the contract is completed
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
7
For millennia
A) construction was almost all masonry
B) contracts did not exist
C) the Architect was also the Builder
D) people built their own structures for themselves
A) construction was almost all masonry
B) contracts did not exist
C) the Architect was also the Builder
D) people built their own structures for themselves
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
8
Projects are usually done
A) with a single builder
B) with a Constructor and several Subcontractors
C) by the Builder that has been chosen by the Architect as most qualified
D) a Design Builder
A) with a single builder
B) with a Constructor and several Subcontractors
C) by the Builder that has been chosen by the Architect as most qualified
D) a Design Builder
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
9
Multi-prime Contracts
A) use more detailed contracts
B) require less supervision
C) separate key trades on the project
D) are seldom used on government work
A) use more detailed contracts
B) require less supervision
C) separate key trades on the project
D) are seldom used on government work
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
10
In horizontal construction, we would expect the Design Professional team to usually be led by an Engineer
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
11
Good Contracts spell out the duty for each party to cooperate
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
12
The Design Professionals are always bound by the same Contract the Owner requires to Constructor to perform
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
13
If at all possible, avoid remedies imposed by courts
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
14
The Owner expects the project to be completed within budget, meeting standards of quality, and it all done safely
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
15
There are three broad types of construction: horizontal, vertical and diagonal
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
16
Engineers are basically needed for horizontal construction but not so much for vertical
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
17
For centuries, the primary concern for design engineering was structural
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
18
Now the electrical and mechanical concerns of buildings must also be engineered carefully
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
19
With few exceptions, Architects have never been Builders
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
20
A risk shifting clause
A) can be passed down to others
B) can affect the General Contractor
C) can affect how Constructors approach a project
D) all of these
A) can be passed down to others
B) can affect the General Contractor
C) can affect how Constructors approach a project
D) all of these
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck