Which of the following is NOT one of Crosby's four absolutes or quality?
A) Make it clear that management is committed to quality
B) Quality is conformance to requirements
C) The standard should be "zero defects"
D) Quality is measured by the cost of nonconformance
Correct Answer:
Verified
Q38: Much of the information contained in a
Q39: The OPM3 cycle consists of four steps:
Q40: Juran Trilogy focuses on the three areas
Q41: To obtain the ISO certification, an organization
Q42: This is the total cost incurred by
Q44: The communications management plan should include description
Q45: This is the time and expense needed
Q46: This is the probability of a product
Q47: This cost is the total cost incurred
Q48: The computer industry, more so than some