Solved

CPM Produces What Key Piece of Information

Question 75

Multiple Choice

CPM produces what key piece of information?


A) The amount of slack, or float, for each activity in the schedule.
B) The critical path, which is the longest path through the schedule or the shortest time in which the project can be completed.
C) Neither A nor B
D) Both A and B

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents