What is the critical path of a project?
A) The path through the schedule with the highest priority tasks.
B) The path through the schedule with the highest cost resources.
C) The longest path through the schedule or the shortest time in which the project can be completed.
D) The shortest path through the schedule.
Correct Answer:
Verified
Q69: Resource _ is the process of rescheduling
Q70: The critical _ method, unlike the critical
Q71: The output from _ planning is used
Q72: Which of the following is NOT an
Q73: The acronym PERT stand for:
A) Program Estimation
Q75: CPM produces what key piece of information?
A)
Q76: Crashing and _ are techniques used to
Q77: What is the deliverable from the project
Q78: This is the cost of a human
Q79: Crashing a project often adds or removes