If Any of the Project Constraints Changes Either by Intended

Question 72

Multiple Choice

If any of the project constraints changes either by intended or unintended factors, the project manager must negotiate ________ in others to keep the project on target.


A) elimination
B) increase
C) reduction
D) changes

Correct Answer:

verifed

Verified