If the client changes his or her mind later in the process, any revisions of the previously approved materials would require a __________, meaning that the client agrees to pay the additional costs for making edits.
A) CMP
B) RFP
C) sign-off
D) change order
Correct Answer:
Verified
Q6: The general rule of thumb when working
Q7: According to the text, during which phase
Q8: What is the typical amount you should
Q9: The end of each phase of the
Q10: Briefly describe the sections of a multimedia
Q11: According to the text, three elements can
Q12: By the time you reach the _
Q13: _ are passed through several levels of
Q14: The proper time to develop a revised
Q15: If your project will take 15 hours