The path in a PERT/CPM precedence network with the fewest activities and shortest duration is referred to as the critical path.
Correct Answer:
Verified
Q10: Although PERT and CPM were originally developed
Q14: One way that project management differs from
Q15: PERT was originally developed for military planning
Q16: A hierarchical listing of what must be
Q17: Project managers bear the ultimate responsibility for
Q20: Following project initiation,planning and scheduling,project execution is
Q21: The standard deviation of a project duration
Q22: For the PERT/CPM technique,completing the backward pass
Q23: Consecutive activities on the same path have
Q24: The standard deviation of the duration of