Consecutive activities on the same path have shared slack,which means if activities are delayed,the amount of slack remaining is reduced for all these activities without delaying completion of the project.
Correct Answer:
Verified
Q5: The latest starting time for an activity
Q10: Although PERT and CPM were originally developed
Q19: The path in a PERT/CPM precedence network
Q20: Following project initiation,planning and scheduling,project execution is
Q21: The standard deviation of a project duration
Q22: For the PERT/CPM technique,completing the backward pass
Q24: The standard deviation of the duration of
Q27: A normal distribution is usually used to
Q28: Activity slack is the difference between the
Q33: In order to determine the probability of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents