Which planning process converts the MPS into requirements for key resources in order to test the feasibility of a proposed MPS?
A) Master production scheduling
B) Aggregate planning
C) Trial-and-error
D) Rough-cut capacity planning
E) Trade-off analysis
Correct Answer:
Verified