Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively, compute the PERT expected activity time for this activity.
A) 10
B) 12
C) 9
D) 11
Correct Answer:
Verified
Q73: In PERT, we assume that
A)the times to
Q74: Given an activity's optimistic, most likely, and
Q75: The project described by: Q76: Table 11-4 Q77: In PERT analysis, the probability of the Q79: Given an activity's optimistic, most likely, and Q80: Table 11-4 Q81: Which of the following is not a Q82: An alternative approach to project crashing is Q83: Reducing the overall activity time is based