Multiple Choice
Table 11-4
The following represents a project with known activity times.All times are in weeks.
-Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?
A) 4
B) 0
C) 8
D) 5
Correct Answer:
Verified
Related Questions
Q71: PERT stands for
A)probabilistic evaluation and review technique.
B)program
Q72: Table 11-4
The following represents a project with
Q73: In PERT, we assume that
A)the times to
Q74: Given an activity's optimistic, most likely, and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents