Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
-Consider the project summarized in Table 11-7.What is the early finish time for Activity D?
A) 19
B) 20
C) 21
D) 22
Correct Answer:
Verified
Q108: Consider the tasks, durations, and predecessor relationships
Q109: Consider the project with the following estimates
Q110: Table 11-7
A project manager calculated early and
Q111: A small software development project has five
Q112: Which of these statements is best?
A)PERT is
Q114: Table 11-7
A project manager calculated early and
Q115: Table 11-7
A project manager calculated early and
Q116: Table 11-8
A mad scientist has identified the
Q117: Given: Q118: Consider the following project schedule:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents