Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.Which of these activities should not be reduced in an effort to deliver a minimum cost (both project and opportunity cost) project?
A) F
B) H
C) G
D) E
Correct Answer:
Verified
Q111: A small software development project has five
Q112: Which of these statements is best?
A)PERT is
Q113: Table 11-7
A project manager calculated early and
Q114: Table 11-7
A project manager calculated early and
Q115: Table 11-7
A project manager calculated early and
Unlock this Answer For Free Now!