Risks on the critical path should be
A) given lower priority than those activities with positive total slack.
B) given equal priority than those activities with positive total slack.
C) given higher priority than those activities with positive total slack.
D) given higher priority than those activities with no total slack.
Correct Answer:
Verified
Q62: Which of the following is not an
Q63: A possible action trigger for rain or
Q64: The possible response plan for vendor delay
Q65: A risk is
A) an uncertain event that,
Q66: The possible impact for rain or snow
Q67: When assigning responsibility for a risk, it
Q68: Risks can be prioritized based on
A) the
Q70: A contingency or management reserve to pay
Q71: A risk response plan can
A) ignore the
Q72: How do the initial risks identified change
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents