The positive cost variance means
A) more money was spent on the project than was planned.
B) more money was spent on the project than the value of the work performed.
C) less money was spent on the project than the value of the work performed.
D) less money was spent on the project than was planned.
Correct Answer:
Verified
Q89: The forecasted cost at completion is
A) a
Q90: The key to managing a cash flow
Q91: The cumulative budgeted cost is
A) the aggregate
Q92: The actual cost on a project is
A)
Q93: If the project has a negative cost
Q95: For a project, the TBC = $200,000,
Q96: The key to managing _ is to
Q97: A cost performance index greater than 1.0
Q98: The first method for determining _ assumes
Q99: Committed costs in a project are
A) those
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents