The Forecasted Cost at Completion Is

Question 89

Multiple Choice

The forecasted cost at completion is


A) a ratio of performance to costs.
B) an estimate of the costs of the work remaining in the project.
C) the planned value of the project.
D) an estimated cost at the completion of the project based on project performance.

Correct Answer:

verifed

Verified