Resource Leveling Attempts to Establish a Schedule in Which Resource

Question 23

Multiple Choice

Resource leveling attempts to establish a schedule in which resource utilization is made as level as possible


A) without extending the project beyond its required completion time.
B) by assigning one resource to work per day.
C) by extending the project beyond its required completion time.
D) by adding additional resources to the project.