A project requires at least 28 worker-days to complete the project.What is the shortest time estimate for completion if the project is constrained to two workers per day? Assume no task requires more than one worker and the tasks can be completed independent of each other.
A) 56 days
B) 28 days
C) 14 days
D) Additional information is needed to determine the project duration.
Correct Answer:
Verified
Q22: Activities drawn in a serial relationship illustrate
Q23: Resource leveling attempts to establish a schedule
Q24: Resource-limited scheduling attempts a schedule in which
Q25: Resource leveling uses a trial-and-error method to
Q26: Resources in a project are
A) human resources
Q28: In _, when several activities need the
Q29: _ is a method for developing the
Q30: _ is an iterative method in which
Q31: When planning a project, it is necessary
Q32: Resources are not usually hired on a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents