Resources are not usually hired on a day-to-day basis to meet fluctuating requirements.This means that
A) the maximum number of project resources should be hired for the project duration.
B) if the workers are employed for the duration of the project and it may be necessary to pay them when idle or overtime when at peak demand.
C) the actual work performed for each activity should be evaluated to inform the next activity of the number of workers needed.
D) all projects should plan all tasks for one person to complete the activities to keep the person busy.
Correct Answer:
Verified
Q27: A project requires at least 28 worker-days
Q28: In _, when several activities need the
Q29: _ is a method for developing the
Q30: _ is an iterative method in which
Q31: When planning a project, it is necessary
Q33: Resource utilization charts based on each activity's
Q34: The resource requirements plan illustrates
A) the utilization
Q35: Resource constraints are represented in the network
Q36: Resource requirements graphs based on an as-soon-as-possible
Q37: Technical constraints for a project are represented
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents