The earliest start time for an activity is
A) the date that all the resources for the project are available.
B) calculated using the project start time and the estimated duration of all of its preceding activities.
C) cannot be earlier than estimated, even if some activities are accelerated.
D) should not be delayed or would cause the project to be delayed.
Correct Answer:
Verified
Q114: To control the project, the project team
Q115: Each activity has two pairs of duration
Q116: The earliest finish time for an activity
A)
Q117: When changes are agreed upon, a new
Q118: The duration of a task is
A) the
Q120: The _ is the estimated cost to
Q121: Schedule updates of the project using actual
Q122: The actual finish time of an activity
A)
Q123: If the project needs accelerated, efforts should
Q124: Schedule control has four steps, they are
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents