The earliest finish time for an activity
A) is calculated by adding the activity's estimated duration to its earliest start time.
B) is the same as the earliest start time of the activity's predecessor.
C) should not be delayed or would cause the project to be delayed.
D) is dependent upon the start time of its successor activities.
Correct Answer:
Verified
Q111: The critical path of a project
A) cannot
Q112: Total slack for a project that is
Q113: The activity bars in a bar chart
Q114: To control the project, the project team
Q115: Each activity has two pairs of duration
Q117: When changes are agreed upon, a new
Q118: The duration of a task is
A) the
Q119: The earliest start time for an activity
Q120: The _ is the estimated cost to
Q121: Schedule updates of the project using actual
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents