Total slack for a project that is negative represents the amount of time that
A) the activities on the path can be delayed and the project still be completed on time
B) all the activities must be accelerated for the project to be completed on time.
C) all the activities can be delayed and the project still be completed on time.
D) the activities on the path must be accelerated for the project to be completed on time.
Correct Answer:
Verified
Q107: When planning the project, it is important
Q108: The _ trade-off methodology is used to
Q109: At the beginning of a longer-term project,
Q110: The _ time is the shortest estimated
Q111: The critical path of a project
A) cannot
Q113: The activity bars in a bar chart
Q114: To control the project, the project team
Q115: Each activity has two pairs of duration
Q116: The earliest finish time for an activity
A)
Q117: When changes are agreed upon, a new
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents