In the network diagram for the following list, what activity immediately follows activity D? Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
C
F
D
G
E
H
F
I
G,H
J
I
A) B
B) C
C) G
D) F
Correct Answer: