__ is a hierarchical tree of end items that will be accomplished or produced by the project team during the project.
A) Work package plan
B) Work budget plan
C) Work contingency plan
D) Work breakdown structure
Correct Answer:
Verified
Q129: Describe the quality standards that must be
Q130: The lowest-level item of any one branch
Q131: For a project, the objective is usually
Q132: The _ is a communication tool for
Q133: _ determines what needs to be done,
Q135: A(n)_ is defined as a piece of
Q136: Draw network diagram for the following project.
Activity
Immediate
Q137: The _ breaks a project down into
Q138: In the planning process, the _ is/are
Q139: In the network diagram for the following