The expected time in PERT is
A) a weighted average of the most optimistic time,most pessimistic time,and four times the most likely time.
B) the modal time of a beta distribution.
C) a simple average of the most optimistic,most likely,and most pessimistic times.
D) the square root of the sum of the variances of the activities on the critical path.
E) None of the above
Correct Answer:
Verified
Q38: Slack is the time an activity can
Q39: CPM stands for Comprehensive Project Method.
Q40: The variance of the project completion time
Q41: Given an activity's optimistic,most likely,and pessimistic time
Q42: Given an activity's optimistic,most likely,and pessimistic time
Q44: PERT
A)assumes that we do not know ahead
Q45: Slack time in a network is the
A)amount
Q46: Given an activity's optimistic,most likely,and pessimistic time
Q47: Given the following small project,the critical path
Q48: According to Table 11-1,compute the slack time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents