Given the following small project,the critical path is ________ days.
A) 10
B) 14
C) 16
D) 20
E) None of the above
Correct Answer:
Verified
Q42: Given an activity's optimistic,most likely,and pessimistic time
Q43: The expected time in PERT is
A)a weighted
Q44: PERT
A)assumes that we do not know ahead
Q45: Slack time in a network is the
A)amount
Q46: Given an activity's optimistic,most likely,and pessimistic time
Q48: According to Table 11-1,compute the slack time
Q49: Managers use the network analysis of PERT
Q50: Given an activity's optimistic,most likely,and pessimistic time
Q51: Given an activity's optimistic,most likely,and pessimistic time
Q52: Table 11-1
The following represents a project with