A project team assigns probabilities of 0.1,0.3,and 0.6 respectively to the maturity,complexity,and dependency categories.The probability of failure can be calculated as:
A) 0.02.
B) 0.45.
C) 0.33.
D) 0.57.
Correct Answer: