With a cost factor of 0.1,a schedule rating of 0.3,a reliability rating of 0.5,and a performance rating of 0.3,the overall consequence of failure was:
A) 0.2 for the squidproofing project.
B) 0.3 for the squidproofing project.
C) 0.4 for the squidproofing project.
D) 0.5 for the squidproofing project.
Correct Answer:
Verified
Q63: A project team assigns probabilities of 0.1,0.3,and
Q64: A project has identical probability of failure
Q65: Fred Knievel took out a substantial life
Q66: Project penalty clauses that initiate at mutually
Q67: If the risk of a negative outcome
Q69: The Farm Fresh Egg project was too
Q70: With the failure probability and consequence scores
Q71: The professor wore both a belt and
Q73: Use the failure probability and consequence scores
Q77: The expected cost of an item that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents