A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology?
A) 13.5
B) 22.5
C) 11.25
D) 9.0
Correct Answer:
Verified
Q43: What are the five steps behind the
Q84: Which of the following statement is best?
A)The
Q85: In order to resolve a resource conflict,it
Q86: A project is represented by the activity
Q87: A project is represented by the activity
Q88: A project is represented by the activity
Q91: A project is represented by the activity
Q92: Use the project information in the table
Q93: A system-wide constraint is called a:
A)rope.
B)resource.
C)drum.
D)chain.
Q94: Use the project information in the table
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents