Solved

A Project Is Represented by the Activity Durations (In Days,estimated

Question 88

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology? A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology?   A) 0 B) 1 C) 2 D) 3


A) 0
B) 1
C) 2
D) 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents