Drum buffers are:
A) a safety margin separating different projects scheduled to use the same resource.
B) extra safety that is applied to a project immediately after the use of the constrained resource.
C) a constraint separating different projects that requires a common buffer.
D) extra safety that is applied to a project immediately before the use of the constrained resource.
Correct Answer:
Verified
Q78: A project consists of six consecutive tasks
Q79: Which of the following statements about CCPM
Q80: A project is represented by the activity
Q81: Successful implementation of CCPM depends on first:
A)identifying
Q82: When choosing the most viable solution to
Q84: Which of the following statement is best?
A)The
Q85: In order to resolve a resource conflict,it
Q86: A project is represented by the activity
Q87: A project is represented by the activity
Q88: A project is represented by the activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents