Which of the following is not something you would use to control risk factors in an information systems project?
A) Internal integration tools
B) External integration tools
C) Formal planning tools and formal control tools
D) Capital budgeting models
E) Gantt charts
Correct Answer:
Verified
Q69: Which type of planning tool shows each
Q70: Which of the following is the most
Q71: External integration tools:
A)enable a project to have
Q72: Which of the following is not a
Q73: Formal planning and control tools:
A)are used to
Q75: To review a project's tasks and their
Q76: Internal integration tools:
A)enable a project to have
Q77: Which of the following is not one
Q78: Which of the following helps project managers
Q79: Which of the following refers to all
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents