To Review a Project's Tasks and Their Interrelationships,you Would Use

Question 75

Multiple Choice

To review a project's tasks and their interrelationships,you would use which of the following?


A) PERT chart
B) Gantt chart
C) PERT chart or a Gantt chart
D) Scoring model
E) Portfolio analysis

Correct Answer: