A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below.
 Task  Duration  (hours)  Predecessors  A 4 B 6 C 2 A  D 6 A  E 3 B, C  F 3 B, C  G 5 D, E, F  H 1 G \begin{array} { | c | c | c | } \hline \text { Task } & \begin{array} { c } \text { Duration } \\\text { (hours) }\end{array} & \text { Predecessors } \\\hline \text { A } & 4 & - - \\\hline \text { B } & 6 & - - \\\hline \text { C } & 2 & \text { A } \\\hline \text { D } & 6 & \text { A } \\\hline \text { E } & 3 & \text { B, C } \\\hline \text { F } & 3 & \text { B, C } \\\hline \text { G } & 5 & \text { D, E, F } \\\hline \text { H } & 1 & \text { G } \\\hline\end{array} a. Draw the appropriate network for this project.
b. What would the cycle time be if the goal is to produce 20 units per month (the plant operates
160 hours per month)?
c. What is the theoretical minimum number of workstations needed?
d. Balance with the most following tasks heuristic. What tasks are assigned to which stations?
e. What is the efficiency of the line obtained in part d?

Correct Answer:

verifed

Verified

blured image blured image (b) The cycle time is 160/20 = 8 hours...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents