A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks which precede each task are:
a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in minutes.
c. Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q134: Briefly explain what "slotting" is. Why is
Q138: "Having a focused work centre is like
Q143: The flow and distance data in
Q144: Cyclone Appliances has developed a new
Q145: A facility is trying to set
Q146: A company is designing a product
Q147: A firm operates a flow shop
Q152: A manufacturing work cell has a takt
Q213: What design guidelines help retail layouts to
Q307: Assembly line balancing has just been used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents