Solved

The Critical Path for the Network Activities Shown Below Is

Question 41

Multiple Choice

The critical path for the network activities shown below is ________ with duration ________.  Activity  Duration  Immediate  Predecessors  A 10 B 8 C 2 A  D 4 A  E 5 B, C, D \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Duration } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 10 & - - \\\hline \text { B } & 8 & - - \\\hline \text { C } & 2 & \text { A } \\\hline \text { D } & 4 & \text { A } \\\hline \text { E } & 5 & \text { B, C, D } \\\hline\end{array}


A) A-C; 12
B) A-D-E; 19
C) B-E; 13
D) A-B-C-D-E; 29
E) A-B-C; 20

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents