Which of the following statements concerning CPM activities is false?
A) The early finish of an activity is the early start of that activity plus its duration.
B) The late finish is the earliest of the late start times of all successor activities.
C) The late start of an activity is its late finish less its duration.
D) The late finish of an activity is the earliest late start of all preceding activities.
E) The early start of an activity is the latest early finish of all preceding activities.
Correct Answer:
Verified
Q74: What is the objective of critical path
Q75: Draw the AOA and AON networks for
Q76: In PERT analysis, the identification of the
Q77: A network consists of the following list.
Q78: A network consists of the activities in
Q80: The PERT pessimistic time estimate is an
Q81: The beta distribution is used in project
Q82: The expected activity time in PERT analysis
Q83: Analysis of a PERT problem shows the
Q84: A project being analyzed by PERT has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents