A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take less than 224 days to complete?
A) near zero
B) 0.0126
C) 0.1587
D) 0.8413
E) 2.14
Correct Answer:
Verified
Q79: Which of the following statements concerning CPM
Q80: The PERT pessimistic time estimate is an
Q81: The beta distribution is used in project
Q82: The expected activity time in PERT analysis
Q83: Analysis of a PERT problem shows the
Q85: A contractor's project being analyzed by PERT
Q86: Which of the following statements regarding PERT
Q87: A project being analyzed by PERT has
Q88: An activity on a PERT network has
Q89: The _ distribution is used by PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents