A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64. What is the probability that the project will take 130 or more days to complete?
A) 0.10565
B) 0.13350
C) 0.85120
D) 0.89435
E) 1.29
Correct Answer:
Verified
Q80: The PERT pessimistic time estimate is an
Q81: The beta distribution is used in project
Q82: The expected activity time in PERT analysis
Q83: Analysis of a PERT problem shows the
Q84: A project being analyzed by PERT has
Q86: Which of the following statements regarding PERT
Q87: A project being analyzed by PERT has
Q88: An activity on a PERT network has
Q89: The _ distribution is used by PERT
Q90: In a PERT network, non-critical activities that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents