Which of the following statements regarding PERT analysis is true?
A) Each activity has two estimates of its duration.
B) Project variance is the sum of all activity variances.
C) Project standard deviation is the sum of all critical activity standard deviations.
D) Only critical activities contribute to the project variance.
E) Only non-critical activities contribute to the project variance.
Correct Answer:
Verified
Q43: The Beta distribution is used in project
Q46: Which of the following statements regarding PERT
Q47: Activity R on a CPM network has
Q51: An activity on a PERT network has
Q53: Activity D on a CPM network has
Q57: The Beta distribution is used in project
Q82: The expected activity time in PERT analysis
Q89: The _ distribution is used by PERT
Q96: The time an activity will take assuming
Q100: Which of the following statements regarding PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents