Activity D on a CPM network has predecessors B and C,and has successor F.D has duration 6.B's earliest finish is 18,while C's is 20.F's late start is 26.Which of the following is definitely true?
A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical,and has zero slack.
E) F is critical,and has zero slack.
Correct Answer:
Verified
Q45: Slack is the amount of time an
Q48: A simple CPM network has three activities,A,B,and
Q51: Which of the following statements regarding critical
Q54: The critical path can be determined by
Q54: Which of the following statements regarding CPM
Q55: The critical path for the network activities
Q56: A simple CPM network has three activities,D,E,and
Q57: The difference between AON and AOA networks
Q58: What is the basic difference between PERT
Q59: The ES of an activity that has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents