Which of the following statements regarding critical paths is true?
A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.
Correct Answer:
Verified
Q46: Every network has at least one critical
Q47: Which of the following statements regarding CPM
Q48: A simple CPM network has three activities,A,B,and
Q53: Activity D on a CPM network has
Q54: The critical path can be determined by
Q54: Which of the following statements regarding CPM
Q55: The critical path for the network activities
Q56: A simple CPM network has three activities,D,E,and
Q58: What is the basic difference between PERT
Q59: The ES of an activity that has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents