Which of the following statements regarding CPM is true?
A) The critical path is the shortest of all paths through the network.
B) The critical path is that set of activities that has positive slack.
C) Some networks have no critical path.
D) All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
E) All activities on the critical path have their ES equal to their LF.
Correct Answer:
Verified
Q45: Activity R on a CPM network has
Q46: Every network has at least one critical
Q46: The network analysis method that allows activity
Q48: A simple CPM network has three activities,A,B,and
Q51: Which of the following statements regarding critical
Q54: The critical path can be determined by
Q55: The _ is a project management technique
Q58: What is the basic difference between PERT
Q59: The ES of an activity that has
Q79: Which of the following statements concerning CPM
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents