Activity R on a CPM network has predecessors M and N,and has successor S.R has duration 5.N's late finish is 18,while M's is 20.S's late start is 14.Which of the following is definitely true?
A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.
Correct Answer:
Verified
Q40: Describe the differences between a Gantt chart
Q41: A simple CPM network has five activities,A,B,C,D,and
Q46: The network analysis method that allows activity
Q46: Every network has at least one critical
Q47: Which of the following statements regarding CPM
Q48: A simple CPM network has three activities,A,B,and
Q54: The critical path can be determined by
Q55: The _ is a project management technique
Q59: The ES of an activity that has
Q79: Which of the following statements concerning CPM
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents