A simple CPM network has five activities,A,B,C,D,and E.A is an immediate predecessor of C and of D.B is also an immediate predecessor of C and of D.C and D are both immediate predecessors of E.Which of the following statements is true?
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are 25 paths in this network.
E) There are six paths in this network.
Correct Answer:
Verified
Q23: What are some of the ethical issues
Q25: The _ has established a code of
Q27: Describe some of the challenges faced in
Q35: What is a project organization?
Q40: Describe the differences between a Gantt chart
Q45: Activity R on a CPM network has
Q46: The network analysis method that allows activity
Q46: Every network has at least one critical
Q55: The _ is a project management technique
Q79: Which of the following statements concerning CPM
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents