Which of the following statements regarding CPM networks is true?
A) There can be multiple critical paths on the same project,all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths,all of them will have the same duration.
E) None of the above are true.
Correct Answer:
Verified
Q45: Slack is the amount of time an
Q50: The _ is the computed longest time
Q51: Which of the following statements regarding critical
Q53: Activity D on a CPM network has
Q54: The critical path can be determined by
Q55: The critical path for the network activities
Q56: A simple CPM network has three activities,D,E,and
Q57: The difference between AON and AOA networks
Q58: What is the basic difference between PERT
Q59: The ES of an activity that has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents